Turnstile installation: how to prepare the site before the gates arrive

Turnstiles are fixed into the floor and wired to the fire alarm, so most of the work happens before the gates are delivered. This guide lists what must be ready on site, in the order the work happens, with a checklist to send with your enquiry.

Glass flap barrier gates in a corporate lobby

What has to be ready before a turnstile installation

A turnstile installation depends on five things being ready before the gates are delivered: the lane layout, the floor and cable routes, power and data at each lane, the readers, and the fire alarm release. Turnstiles are fixed into the floor and wired to the fire alarm, so the survey and the preparation matter more than for most systems.

Our turnstile installation in Dubai page shows the gates we supply. This guide covers the site work around them, in the order it happens. If you are still choosing a gate, read our comparison of the types of turnstiles first.

Step 1: survey the entrance and settle the lanes

The survey settles three things: how many lanes, where the wide lane goes, and whether the gates stand indoors or outdoors.

  • Peak flow. The number of people arriving in the busiest 15 minutes decides the number of lanes. Count it at the real peak, such as a shift change.
  • Accessible lane. Plan a wide lane for wheelchairs, prams, trolleys and deliveries from the start. It needs more floor width than a standard lane.
  • Indoor or outdoor. Dust, heat and rain decide the model and finish.

What each type needs from the site

Each type needs something different from the site. The figures are for the models we currently supply.

Tripod turnstileFlap barrierFull height turnstile
Where it standsIndoors or under coverIndoorsOutdoors, at perimeters and gates
Typical locationStaff entrances, gyms, factoriesOffice towers, hotel and residential lobbiesWarehouses, labour accommodation, construction sites
SpaceUnit 1200 × 280 × 980 mm, arms 510 mmUnit 1400 × 300 × 1000 mm, lanes 600 mm or 900 mm wideUnit 1550 × 1550 × 2300 mm, single or dual lane
Floor workFixed into the floor, with a cable route to each unitFixed into the floor, with cable routes planned before the finish goes downBase and power checked on the survey

Step 2: prepare the floor and the cable routes

The floor holds the fixings and hides the cables. Each unit is fixed into the floor and its cables normally come up beneath it, so the survey checks the finish, the screed depth and where cables can run to each lane.

In a new fit-out

Conduits are easiest to lay before the screed and floor finish go down. Agree the lane positions with the fit-out contractor early, run a conduit to each unit position and leave a draw wire in it. In a flap barrier lobby with a stone or tile floor, this avoids cutting a finished surface.

In a finished lobby

In a finished lobby the cable route has to be found. The usual options are a chase cut into the floor and made good, a route up through the slab from the level below, or an existing raised floor. Each affects the finish or the structure, so get building management's agreement before anyone cuts or drills. Most buildings in Dubai ask for drawings and a method statement before contractors start.

At an outdoor gate

A full height turnstile, the high security choice for perimeters, stands in the open, so the checks change. The base is checked on the survey, power has to reach the gate and readers on the lane should be shaded. The unit we supply is 2,300 mm tall, so check the headroom under any canopy.

Step 3: bring power and data to each lane

Each lane needs mains power and a connection to the access controller, both in place before installation day. All three models we supply run on 100 to 240 V AC.

  • Power. Ask your electrician for a mains supply at the lane positions, in its own conduit.
  • Signal. The tripod and full height turnstiles take a Wiegand or dry contact signal from the access controller. The flap barrier can also connect over TCP/IP, which needs a network point at the lanes.
  • Readers. Matrix COSEC devices such as the ARGO FACE terminal and the ARC DC200P controller connect over Ethernet and can be powered over PoE, so each needs a network cable back to a PoE switch.

Where a separate controller is used, fix its position and that of its power supply before the conduits are laid, because the cables from each lane run back to it. Turnstile systems rely on a controller that holds the users and rules, so the lanes keep working if the network drops, and on a battery-backed power supply that carries readers and controller through a short power cut. Both need a secure place an engineer can reach.

Step 4: choose the readers for each lane

Each lane reads the same cards, faces or QR passes as your doors, so choose the readers as part of your access control system, not as a separate purchase. In turnstile access control the reader identifies the person, the controller decides and the gate only opens the lane.

Settle these before ordering:

  • Direction. Decide whether people are checked on the way in only, or on the way out as well. A controlled exit needs a reader on the exit side.
  • Visitors. If guests will use QR passes from the visitor management system, put a QR reader on at least one lane. The pass works only where you allow it and only during the visit.
  • Attendance. When the lane readers are part of Matrix COSEC, every pass through the gate can count as an attendance punch. Say so early, because it affects which directions are controlled.
  • Enrolment. Staff already enrolled on the doors use the same card or face. Enrol anyone new before the first morning.

Step 5: agree the fire alarm release

The fire alarm signal must release every lane for free passage, and the connection has to be agreed with the fire alarm contractor before installation. When the alarm activates, tripod arms drop or rotate freely, flap barriers open and a full height turnstile is released to rotate freely.

We make the connection together with your fire alarm contractor. Have these ready:

  • The contractor's name and contact details
  • Agreement on where the release signal is handed over, at the lanes or at the controller
  • A date when the contractor can attend the test

In a multi-tenant building the fire alarm is often the landlord's system. Ask building management who may work on it and how much notice they need.

Step 6: test every lane before handover

Handover should follow a test of every lane, not a demonstration on one. We test with you on site, and these are the checks to witness:

  1. Each lane in both directions. Walk through every lane, in and out, with a valid credential and without one.
  2. Real credentials. Use actual staff cards and enrolled faces, a visitor QR pass issued that day and a blocked card.
  3. The accessible lane. Take a wheelchair, pram or loaded trolley through the wide lane.
  4. The fire release. Have the fire alarm contractor trigger the signal and check that every lane goes to free passage. Then check how the lanes return to normal after the reset.
  5. Records. Confirm that each pass appears in the access log and, if you use it, as an attendance punch.

At handover, ask for the test sheet, the admin logins, the warranty details and an as-built drawing that shows the cable routes under the floor. With a tripod turnstile, also ask who holds the manual override key that releases the lane in a power failure.

Preparation checklist to send with your enquiry

Send what you can from this list with your enquiry. We then check the floor and the fire alarm interface on the survey and quote per lane.

  • A floor plan of the entrance, even a rough one, and photos of the floor
  • The number of people entering in the busiest 15 minutes
  • Whether the gates will stand indoors, under cover or in the open
  • The floor finish, whether it is laid yet or the date it will be, and what is below it
  • The make of your access control system and readers, if you have one
  • Whether visitors will use QR passes, and whether gate passes should count as attendance
  • Contacts for the fire alarm contractor and building management

Questions

How many people can one turnstile lane pass in a minute?

The tripod turnstile we supply passes up to 30 people a minute and the flap barrier up to 40. A full height turnstile is slower, because one person passes per rotation.

Can turnstiles connect to our existing access control system?

Usually. The tripod turnstile we supply connects to Matrix COSEC or any other access controller over Wiegand or dry contact, and the flap barrier and full height turnstile use the same interfaces. We check the make and spare controller capacity of an existing system on the survey.

Is floor work included in a turnstile quote?

It is priced as its own line. Flap barriers, for example, are quoted per lane after a site check, with the wide lane, readers, finish and floor work listed separately.

Can one turnstile control both entry and exit?

Yes. The tripod and full height turnstiles we supply are bi-directional, and on the full height turnstile each direction can be set to controlled or free.

Send us your entrance details

Tell us the peak number of people in the busiest 15 minutes and where the gates would go, and we will check the floor and fire alarm interface on the survey.

+971 55 288 6114Call or WhatsApp, Monday to Saturday, 9:00 to 18:00
info@oneexpertis.comFloor plans and tender drawings welcome (PDF or DWG)
Al Wasl Building, Bur DubaiOffice 139, F5-B, Fifth Floor, near Bur Dubai Civil Defence
Please enter your name.
Please enter a number we can call, for example +971 50 123 4567.
Please choose the type of premises.

Sends your details to us on WhatsApp. We use them only to arrange your survey.

WhatsApp us