Why cabling quotes for the same office differ
A network cabling quote is hard to compare with another because each bidder decides what to count, what to include and what to leave out. One network cabling company prices "40 data points", another writes "structured cabling, lump sum", and neither says what sits behind the words. The gap between the totals usually comes from seven places:
- Cable grade: Cat6 or Cat6A, the brand, and whether the jacks and patch panels match the category of the cable.
- What a "point" includes: for one bidder it is the cable run alone; for another it is the cable, the outlet, the patch panel port, termination, testing and a label.
- Containment: new tray, trunking or conduit may be priced, assumed to exist already, or left to the fit-out contractor.
- Testing: a continuity check and certification of every link are different amounts of work.
- Rack and patching: the rack, patch panels, cable managers and patch cords are sometimes inside the price and sometimes not.
- Labour outside working hours: in an occupied office, ceiling work and drilling often have to wait for the evening or the weekend.
- Building management paperwork: Dubai buildings commonly want drawings and a method statement before work begins, and someone has to prepare them.
We quote our own network cabling services in Dubai as separate items for this reason.
The line items a complete quote should show
A complete quote lets you fill in every row below without phoning the bidder. Copy the rows into a sheet, add a column for each quote and write in what it says. An empty cell is a question to send back, not a saving.
| Line item | What to look for |
|---|---|
| Outlets: number and location | A count per room or area that matches a marked-up floor plan, and a note on whether a double outlet counts as one point or two. |
| Cable category and brand | Cat6 or Cat6A, the manufacturer, unshielded or shielded, the sheath type, and solid copper conductors rather than copper-clad aluminium. |
| Cable length or route | Metres measured on site, or at least the route and the longest run. A length scaled from a drawing is an estimate. |
| Containment | What is new, what is existing and who supplies it: tray in the ceiling, trunking or conduit down to each outlet, and fixings. |
| Patch panels, rack and cable management | Rack height in U, wall or floor mounting, the number of patch panels and cable managers, and whether patch cords are included. |
| Faceplates and floor boxes | Single or double plates, floor boxes for desks away from a wall, and jacks of the same category as the cable. |
| Fibre backbone, if any | Fibre type, number of cores, where each end terminates and how it will be tested. |
| Testing method | The word "certified", the tester named and the standard tested against, for every link. |
| Labelling | One number shared by the outlet, the patch panel port and the drawing, on printed labels. |
| As-built drawing | A drawing issued after installation that shows outlet numbers and cable routes, handed over as a file. |
| Warranty | Separate terms for the cabling products and for the workmanship, each with its period and who honours it. |
| Programme of dates | Start and finish dates, when each area will be disturbed, and any work outside office hours. |
| Exclusions | A written list of what is not priced, such as switches, patch cords or closing up the ceiling. |
Compare like with like: if one quote is for Cat6 and another for Cat6A, ask both bidders to price the same category before you compare totals. Our guide to Cat6, Cat6A and fibre for a Dubai office explains which suits which use.
Continuity test or certification: what "tested" means
A continuity test and a certification test are different things, and a quote that only says "tested" could mean either. A continuity or wire-map tester confirms that each of the eight wires is connected from end to end in the right order, so it finds a broken or crossed wire. It does not show that the link performs as Cat6 or Cat6A.
Certification does. A certifier measures the installed link across the frequencies its category has to carry, compares the readings with the limits in the cabling standard and records a pass or fail for that link, with its length. A cable can pass a continuity check and still fail certification because of a poor termination, a tight bend or a run that is too long.
Why the test report matters
The test report is your evidence that you received the category you paid for. It should list every link by the number on its label, with the category and standard it was tested against, its length, the result and the date. If a port misbehaves later, the report shows whether the cable was sound at handover, which narrows the fault-finding.
On our structured cabling installations we run a Fluke DSX-5000 certification test on every permanent link (the fixed cable from patch panel to outlet) and give you each link's result along with the as-built drawing.
Questions to ask each cabling contractor
Send the same seven questions to every network cabling contractor on your list, in writing, so that the answers become part of the quote.
- Which standard do you install and test to? Expect a named standard, such as TIA-568 or ISO/IEC 11801, not "industry standard".
- Can we see a sample test report? It should be exported from the tester and show one result per link, not a single line saying that everything passed.
- Who does the work? Ask whether the installers are the company's own technicians or a subcontractor, and who supervises on site.
- How are outlets and panel ports labelled? Ask for the numbering scheme and a photo of a rack they have finished.
- Which drawings do we receive, and when? Expect a marked-up plan with the quote and an as-built drawing at handover.
- What hours will you work? Ask which tasks are planned outside office hours, and who prepares the documents building management wants.
- Who maintains the cabling afterwards? Find out how faults and extra points are handled once the job is closed.
Our own answer to the last question: cabling faults and re-patching are included in our IT annual maintenance contract, for clients who take one.
Red flags in a cabling quote
A red flag in a cabling quote is anything that stops you seeing what is included, and it calls for a question rather than a rejection.
- A single lump sum with no quantities.
- "Cat6 cable" with no brand, or cable and jacks of different categories. A link performs only as well as its lowest-rated part.
- "Testing included" with no tester named and no mention of a report.
- Containment not mentioned, or "existing containment to be used" when nobody has looked above the ceiling.
- A firm price given without a site visit.
- No drawing, labelling or handover documents listed.
- No exclusions. A quote that excludes nothing has not necessarily included everything.
- A total far below the others. Find the missing line before treating it as the better price.
What to send to get a comparable quote
Send every bidder the same four things, so that each one prices the same job.
- A floor plan with desk positions: PDF or DWG, with printers, meeting rooms and the comms room or rack location marked.
- A device list: everything that needs a cable, listed room by room, including computers, phones, printers, cameras, door readers and Wi-Fi access points.
- The ceiling type: removable tiles, closed gypsum or open ceiling, plus photos of any existing rack and tray. This decides the containment and much of the labour.
- The building rules: permitted working hours, the documents building management asks for and a contact name there.
Ask each network installation company to reply using the line items in the table above. If you would like us to be one of the bidders for your office cabling, book a site inspection: an engineer walks the site, we mark outlets and cable routes on your plan, and we price the outlets, cable, rack and network equipment as separate lines, with a programme of dates.
Questions
Should switches and Wi-Fi access points be on the same quote as the cabling?
They can come from the same company, but ask for them as separate lines or a separate package so the cabling can be compared on its own. Onexpertis prices network equipment separately from the outlets, cable and racks.
What happens if a link fails its certification test?
The installer should find the cause, re-terminate or replace the cable and test again, so that the report you receive shows a pass for every link. Ask each bidder to confirm in writing that this rework is inside their price.
We already have a BOQ or tender drawings. Is that enough to get comparable quotes?
Yes. A BOQ gives every bidder the same quantities, so the quotes start from the same scope. Onexpertis prices from the client's drawings and BOQ, then visits to confirm site conditions before the final quote.
When in a fit-out should the cabling quote be agreed?
Before the ceiling is closed, because the trays and cable routes sit above it and adding a point later means ceiling work. On a new office we work from the fit-out drawings and coordinate ceiling and containment work with the fit-out contractor.